In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including   ( )。

2021-11-09 15:12:52 薄心之心 1081

In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including   ( )。

A.budget 

B.plan 

C.risk 

D.contract

参考答案:C

参考解析:在估算成本时,估算者会考虑成本估算偏差的潜在原因,包括风险。